PML MEMBER NOTICE: PGE Update as of 6/6/2025

PG&E is working hard to stay on schedule and be supportive to PML. Here is the update for this week.

  • The Civil team is currently working on Pine Mountain Drive.  KW Emerson will finish trenching and installing boxes next week.
  • The Electrical team is finishing work on Elder Lane this week and then will begin to work on Pine Mountain Drive.
    • Note: the electrical process is not as involved as the civil and tends to be more flexible.
  • Both teams will be working on Pine Mountain Drive this coming Sunday (6/8/25).
  • There will be multiple traffic crews working and coordinating together. The wait time for drivers is anticipated to continue to be 15-20 mins per stop.
  • PML has requested that 8 PM be the latest crews work on any given day.
  • Their goal is to be done with civil and electrical by June 28, 2025. All teams will pause through the Independence Day weekend. Then restoration to the roads will be completed after the holiday weekend.
  • The 2026 plan is coming out of design. PG&E will start to reach out to property owners to gain right of entry (ROE) to place boxes next year.

New work schedules to be released soon.