PMLA MEMBER NOTICE: PG&E Update
You can expect to see K.W. Emerson, Inc. working between Tannahill and Grizzly from 5/20 through 5/25.
The goal is to limit delays over the weekend. If you are driving this section of Pine Mountain Drive, please drive slow and safe when following the pilot truck.
The main trenching is anticipated to be wrapped up by this Saturday, which also means less trucks. This will have a positive impact on traffic.
Sunday (5/26) and Monday (5/27) no road work is scheduled.
**More information to come regarding the details of this weekend**
You may access this information and other PGE related items via our PML website in the members area –> https://www.pinemountainlake.com/pge-power-line-undergrounding-project/
Click to access CURTIS-1703_-3-Week-Look-Ahead_Groveland-5.21.pdf