PG&E ~ Phase 2 of the Underground Project is underway.
Here is the update for this week.
- The Civil team is currently working on Pine Mountain Drive between Mills and Casaretto, and along Elder Lane.
- As of October, the Electrical team is working alongside the civil team.
- There will be a total of 4 teams in October:
- 1 team on Elder Lane
- 1 team at the Main Gate
- 2 teams between Casaretto and Butler Way
- The teams are working on Pine Mountain Drive Monday through Saturday from 7 am until 7 pm until November 1st.
- There is one lane traffic control.
- The wait time for drivers is anticipated to be 10-15 mins per stop.
- PG&E will reach out to property owners to gain right of entry (ROE) to place boxes during this phase of the project.
For more information call Carlos, the Senior Outreach Specialist, from PG&E at 1 (209) 981-8550.
This project phase is scheduled to be completed by November 1st, 2025.