PG&E has started Phase 2 of the Underground Project. This project phase is scheduled to be completed by November 1st, 2025.
Here is the update for this week.
- The Civil team is currently working on Pine Mountain Drive between Mills and Casaretto.
- The team is working on Pine Mountain Drive Monday through Saturday from 7 am until 7 pm until November 1st.
- There is one lane traffic control.
- The wait time for drivers is anticipated to be 10-15 mins per stop.
- PG&E will reach out to property owners to gain right of entry (ROE) to place boxes during this phase of the project.
For more information call Carlos, the Senior Outreach Specialist, from PG&E at 1 (209) 981-8550.