PML Member Notice: PG&E Update – 03/26/2026

PML MEMBER NOTICE – PG&E Project Update

POSTED: March 26, 2026.

  • The following streets are scheduled to be demobilized by May 8th: Tannahill Drive, Pine Mountain Drive, Grizzly Circle, Butler Way, Elder Lane, Salvador Court, and Fountain Circle. This is considered the “end of that phase”.
  • On April 20th another phase begins on these streets: Pleasant View Drive, Chaffee Circle, Mt. Jefferson, and Reid Circle.
  • PG&E anticipates both projects to be concluded by June.

Please see the PG&E project “Look Ahead” schedule below for the current work on Tannahill Drive, Fountain Circle, Grizzley Circle, Salvadore Court, Pine Mountain Drive, and Elder Lane.

For more information regarding the PG&E work, please contact PG&E Outreach Specialist Carlos Martinez at 1(209)981-8550.

 